Bradbury Dam, Lake Cachuma

Project Description

The Bradbury Dam Radial Gates Maintenance and Modification including removal and replacement of existing coatings and gate extension construction was an 8-month $2.6 million project that was completed in June of 2004.

Scope of Services

DESIGN – Construction document assembly and gate extension design modification.

CONSTRUCTION – Construction contract administration, construction monitoring and review; coordination of materials testing and inspecting; monitoring of welding and monitoring and testing of coating application.